Budget Estimation
Budgeted Costs for Sample Project
Duration (in weeks)
5
10
15
20
25
30
35
40
45
Total
Design
6
2
1
9
Engineer
5
10
12
6
33
Install
7
15
30
8
60
Test
1
5
8
5
2
12
Total Monthly Cumul.
6
13
31
58
95
108
116
121
123
114,000
Monthly Budget of a project
Design = $ 9,000
Engineer =$ 33,000
Install = $ 60,000
Test =$ 12,000
Therefore, the total budget would be = $144,000
However, the monthly budget would be Total budget divided by the number of months.
Monthly budget would be =
The month budget of the project = 9,000+13,000+60,000+12,000 = 114,000
The monthly budget would then be $114,000 divided by 42
Monthly budget would be = $2,714.28
Cumulative budget would be the total of amout spends on a project in a month.
= 6+13+31+58+95+108+116+121+123
= 123,0000
Monthly cumulative = $123,000
B. Draw a project S-curve identifying the relationship between the project’s budget baseline and its schedule
Graph 1: Relationship between project baseline and Schedule
The graphic indicates that there is a relationship between the schedule and the budget. The budget increase depends on the schedule. At the beginning of the schedule, the amount spend was less and it increases as the days and schedule move on.
4. Using the data in the table below, complete the table by calculating the cumulative planned and cumulative actual monthly budgets through the end of June. Complete the earned value column on the right. Assume the project is planned for a 12-month duration and $250,000 budget.
Activity Jan Feb Mar Apr May Jun Plan % C Value
Staffing 8 7 15 100
Blueprinting 4 6 10 100
Prototype
Development 2 8 10 70
Full Design 3 8 10 21 67
Construction 2 30 32 25
Transfer 10 10 0
Monthly Plan 98
Cumulative 362
Monthly Actual 10 15 6 14 9 40
Cumul. Actual 80
More Subjects
Join our mailing list
@ All Rights Reserved 2023 info@freeessaywriter.net