Problem 1
Project A Payback Time = $250,000/$75,000 = 3.3 years.
Project B Payback Time = $150,000/$52,000 = 2.9 years
Therefore, Project B will be a better option
Problem 3
NPV = -75 + 20/(1.2) + 25/(1.2)2 + 30/(1.2)3 + 50/(1.2)4
= $501.5432
Problem 4
The investment will become unfavorable with the barrier of 24%